Holy Trinity Church, Wandsworth

Holy Trinity Church Wandsworth

Refurbishment within the existing church including new heating, electrical, audio and organ installations along with new finishes throughout and creation of new room layouts to back office areas. In addition the works comprised the construction of a new extension linking the church to the adjacent parish building, providing additional offices space, and redevelopment of the external spaces including a new courtyard area.

The project will be finished in June 2014. The cost of works is in the region of £1m.

RLP Roles: Chartered Quantity Surveyor, CDM Coordinator
Architect: HMDW
Contractor: Farnrise Construction Ltd